You've chosen your generator, signed the contract, and scheduled the installation. Now what? Understanding the installation process helps you prepare your home and sets realistic expectations. Here's a detailed look at what happens during a professional standby generator installation.
Key Takeaways
- Medical equipment like CPAP machines, oxygen concentrators, and home dialysis systems require uninterrupted power.
- A standby generator with automatic transfer switch provides the fastest, most reliable backup for medical needs.
- Battery backup (UPS) systems bridge the 10-second gap between outage detection and generator power-up.
- Register with your utility company as a medical-priority customer for faster power restoration during outages.
Before Installation Day
Site Preparation
Before we arrive, you may need to:
- Clear the installation area of obstacles, furniture, and plants
- Ensure gate access for equipment and materials
- Mark sprinkler heads or underground utilities in the work area
- Relocate vehicles from the driveway/work area
- Secure pets away from the work zone
Utility Coordination
We handle utility coordination, which may include:
- Gas company visit to assess line capacity
- Electric utility notification
- Miss Utility marking of underground lines
- Propane tank delivery scheduling (if applicable)
Critical Setup: Pair your standby generator with a battery backup (UPS) on the circuit powering medical equipment. The UPS provides instant power during the 10-second transfer switch delay, ensuring zero interruption to life-sustaining devices.
Installation Timeline Overview
Most residential installations take 1-2 days:
Never lose power again. We are authorized Generac installers serving all of Northern Virginia. From sizing to installation to maintenance, we handle every step. Call (703) 997-0026 for a free in-home assessment.
- Day 1: Site prep, pad installation, generator placement, fuel line
- Day 2: Electrical connection, transfer switch, testing
- Complex installations: May require 3 days
Day 1: Site Work and Generator Placement
Morning: Site Preparation (8:00 AM - 10:00 AM)
- Crew arrival and equipment unloading
- Final site measurements and marking
- Excavation for pad (if poured concrete) or leveling for composite pad
- Trenching for electrical and fuel lines (if underground)
Mid-Morning: Pad Installation (10:00 AM - 12:00 PM)
- Composite pad: Level ground, place pad, secure
- Concrete pad: Form work, pour concrete (may need to cure before proceeding)
- Verify level and proper positioning
Afternoon: Generator Placement (1:00 PM - 3:00 PM)
- Generator delivery (large truck with lift gate)
- Careful placement on pad using equipment or crew
- Anchor generator to pad (if required)
- Verify clearances and orientation
Late Afternoon: Fuel Line Installation (3:00 PM - 5:00 PM)
- Run gas line from meter to generator location
- Install proper fittings, shutoff valve, and connections
- Pressure test the line (required by code)
- Backfill trenches if underground
Day 2: Electrical Work and Commissioning
Morning: Transfer Switch Installation (8:00 AM - 11:00 AM)
- Power shutoff (your home will be without power for 1-3 hours)
- Install automatic transfer switch near/in electrical panel
- Connect transfer switch to utility and panel
- Run control wiring between generator and ATS
Late Morning: Generator Electrical Connection (11:00 AM - 1:00 PM)
- Run power cable from generator to transfer switch
- Make all electrical connections at generator
- Install conduit and protect exposed wiring
- Connect generator control wiring
Afternoon: Testing and Commissioning (1:00 PM - 4:00 PM)
- Restore utility power
- Program generator control settings
- Perform initial startup and safety checks
- Simulate outage to test automatic operation
- Verify all circuits transfer correctly
- Load test the generator
- Check for proper operation under various conditions
Wrap-Up (4:00 PM - 5:00 PM)
- Clean up work area
- Final site inspection
- Homeowner orientation and training
- Paperwork and warranty registration
What You'll Experience
Noise
Expect construction noise from:
- Trenching equipment (if underground lines)
- Generator movement and placement
- Power tools and drilling
- Generator testing
Power Outage
Plan for 1-3 hours without power when we connect the transfer switch. We'll coordinate timing with you. Plan accordingly:
- Don't schedule work calls requiring computers
- Medical equipment users should have battery backup
- Avoid opening refrigerator/freezer during outage
Yard Impact
- Trenches will be backfilled and seeded if needed
- Some minor landscaping touch-up may be required
- Heavy equipment may leave temporary marks
Homeowner Training
Before we leave, we'll show you:
- How to check generator status
- What indicator lights and codes mean
- How to perform manual operation if needed
- Where to find fuel shutoff
- How to use the monitoring app
- Maintenance schedule overview
- Emergency contact information
After Installation
Inspection
We schedule required inspections with the county. These typically occur within 1-2 weeks and require access to the generator and electrical panel.
First Exercise Cycle
Your generator will run its first automatic exercise cycle at the scheduled time (usually weekly). Don't be surprised when you hear it start!
Monitoring Setup
We'll help you set up the manufacturer's app so you can monitor your generator from anywhere.
Professional Installation Matters
A proper installation ensures:
- Code compliance and successful inspection
- Valid manufacturer warranty
- Safe operation for decades
- Reliable performance when you need it
- Insurance acceptance
At AJ Long Electric, we've performed hundreds of generator installations across Northern Virginia. Contact us to schedule your installation and experience our professional, thorough process.
Tags:

Written by
Matt Long
Master Electrician
Our team of licensed electricians brings over 40 years of combined experience serving Northern Virginia. We're committed to providing expert electrical solutions with a focus on safety, quality, and customer satisfaction.
Reviewed by AJ Long Electric Master Electricians · VA License #2705031092 · View Credentials



